FY2020 Capital Maintenance Program

Project Overview

NNEPRA partners with Pan Am Railways annually to develop maintenance programs to improve infrastructure and enhance freight and passenger rail operations. Programs may include the maintenance of ties, communication and signal equipment, grade crossings, and brush cutting.  


What to expect in the coming months.

Date Goal
June 2020 Grade Crossing Improvements in Newfield, Newton, and Kingston New Hampshire
July 2020 Fore River Bridge Timber Improvements

Project Budget

The total project budget is $833,887.
Eighty percent of the project is being financed using federal funding sources, with Pan Am Railways contributing the remaining 20% match.

Project Schedule

Estimated Completion Date: Winter 2020