FY2020 Tie Replacement Project

Project Overview

Approximately 30 miles of Mainline track between Dover and Plaistow, NH, benefited from the selective replacement of 15,000 mainline railroad ties and tie plates (including removal and disposal), the addition of 5,000 tons of stone ballast, and final surfacing and alignment.

Date Milestone Achieved
May 2020 Procurement of Materials
June 2020 Construction Began
July 2020 Construction Completed

Project Budget

The total project budget is $2,242,970.
Fifty-seven percent of the project was financed using federal funding sources, with PanAm Railways contributing the remaining 43 percent match.

Project Schedule

This project was completed July 2020